2-Storey Dwelling House at 42/44 Jalan Limao Bali
Start Date: 3 March 2000
Completion Date: 9 June 2000
Description: A&A works to existing houses, increasing its floor area by 30% and all renovation works.
2-Storey Bungalow with an Attic and Swimming Pool |

Fish Farm on Plot LCK 170 MK 12
Start Date: 20 March 2000
Completion Date: 20 June 2000
Description: Full sub-contract from main contractor, consisting of 1 no. 30mx100m aquarium block, an extension of existing show room, 1 pump room and 1 toilet block.
Fish Farm on Plot LCK 170 MK 12 |

RC Building & Workshop
Start Date: 01 April 2000
Completion Date: 30 September 2000
Description: Construction of 4 on-guard CD shelter blocks, 304, 304A, 316 & 317.
RC Building & Workshop |

Tuas A Power Station Stage II Development
Start Date: 22 April 2000
Completion Date: 31 July 2000
Description: Jian Huang was engaged for the conduit and water treatment plant works on this delayed project.
Tuas A Power Station Stage II Development |
2-Storey Bungalow with an Attic and Swimming Pool
Start Date: 20 July 2000
Completion Date: 5 January 2001
Description: Construction of a bungalow as designed by WH Architects incorporating the latest trend.
2-Storey Bungalow with an Attic and Swimming Pool |

Irrawaddy Road & Extension of Shan Road Work
Start Date: 3 October 2000
Completion Date: 14 June 2001
Status: Full Sub Contract
Client:CWT Limited
Description: Full sub-contract from main contractor, who has a 6-month delay, and with direct payment from LTA. This road widening was specifically for MHA complex, which was officially open on 8 August 2001. we achieve great success by completing the project in 9 months’ time (the contract duration was 12 months) setting a benchmark for our construction philosophy.
Irrawaddy Road & Extension of Shan Road Work |

HDB Apartment at Punggol
Start Date: 1 October 2000
Completion Date: 30 November 2000
Description: Jian Huang was engaged in this project specificallt to assist ECON Piing in completing the balance sub-structure works for 3 blocks of HDB apartments and a car park within 2 months.
HDB Apartment at Punggol |

Sungei Sembawang Kechil Abstraction Pond & Ancillary Facilities
Start Date: 1 November 2000
Completion Date: 28 November 2001
Description: Construction of PUB modern water pond for storage of recycle water discharge from HDB estates.
Sungei Sembawang Kechil Abstraction Pond & Ancillary Facilities |

1 Pair of Dwelling Detached House
Start Date: 10 February 2001
Completion Date: 25 July 2001
Description: Construction of structural works, including 1 basement and 3-storey building.
1 Pair of Dwelling Detached House |

Surface Drains at Sengkang LRT
Start Date: 01 August 2001
Completion Date: 15 October 2001
Description:Construction of 300mm wide center median drain along LRT viaduct.
Surface Drains at Sengkang LRT |

6.6KV Substation at Cluny Hill
Start Date: 08 October 2001
Completion Date: 8 January 2002
Description: Full subcontract of a single-storey 6.6KV substation.
6.6KV Substation at Cluny Hill |
3-Storey House at No.19 Third Street
Start Date: 22 November 2001
Completion Date: 19 December 2002
Status: Main Contractor
Description: Re-construction of a 3-storey house.
3-Storey House at No.19 Third Street |

6.6KV Substation at Clementi ITE
Start Date: 16 January 2002
Construction Duration: 15 March 2002
Description: Full subcontract of a single-storey 6.6KV substation.
6.6KV Substation at Clementi ITE |

6.6KV Substation at NTU
Start Date: 16 February 2002
Completion Date: 15 March 2002
Description: Full subcontract of a single-storey 6.6KV substation.
6.6KV Substation at NTU |

DTSS (Deep Tunnel Sewerage System)
Start Date: 25 March 2002
Completion Date: 15 February 2002
Description: Construction for the 30m deep sewerage tunnel work.
DTSS (Deep Tunnel Sewerage System) |

Irrawaddy Road & Shan Road
Start Date: October 2000
Completion Date: June 2001
Description: Widening of Irrawaddy Road and extension of Shan Road; total 2km length. Specifically built for MHA Complex.
Irrawaddy Road & Shan Road |
Aqua Fauna Centre
Project Start Date: April 2002
Project Completion Date: October 2002
Client: Aqua Fauna International Pte Ltd
Description: Modern 7 blocks, single-storey werehouse with ample car park and landscape for a modern fish market. Promoted as a tourist attraction at eastern Singapore by Tourist Board.
Aqua Fauna Centre |
|
|
|